KINSHASA, Nov 26 – The Democratic Republic of Congo (DRC) is planning to establish two gold refineries with a combined annual processing capacity of 68 metric tonnes, as the government seeks to formalise gold production, reduce illicit cross-border trade and strengthen its control over the country’s mineral resources.
DRC Gold Trading SA, the state-owned gold trader, announced the plans on November 25, 2026, outlining a 50-tonne-per-year refinery in Kinshasa and a second facility with annual capacity of 18 tonnes in Kisangani, according to Bloomberg News.
The Kinshasa facility, which is being developed through a joint venture with UAE-based Metahive Ltd, will serve as the flagship project.
The company said it could eventually pursue certification from the London Bullion Market Association (LBMA), a step that would support access to internationally recognised bullion markets, subject to meeting the association’s requirements.
The planned Kisangani refinery will have capacity to process 18 tonnes of gold annually, expanding the country’s proposed refining infrastructure beyond the capital.
Together, the facilities would provide processing capacity of 68 tonnes a year, roughly 60% above the DRC’s formal gold production recorded in 2025.
Formalising artisanal gold production
The refinery programme builds on DRC Gold Trading’s mandate to bring artisanal gold production into the formal economy. The company was originally established in 2023 as Primera and is tasked with improving traceability and reducing the movement of gold through illicit trading networks into neighbouring countries, including Rwanda and Uganda.
Artisanal and small-scale mining remains an important part of the DRC’s gold sector, but weak traceability and informal trading channels have limited the government’s ability to capture the full economic value of production.
Developing domestic refining capacity could provide a formal route for processing locally sourced gold, while improving the government’s ability to monitor volumes, establish supply-chain records and retain more value within the country.
The expansion follows the launch in March 2026 of a state-backed pilot refinery in Kalemie, developed in partnership with Lunga Mining. The facility has processing capacity of up to 600 kilograms per month and produces gold at a reported purity of 99.9%.
The two proposed refineries would significantly expand the country’s planned processing capacity beyond the pilot operation.
Central bank demand and official gold reserves
The Central Bank of the Congo has become DRC Gold Trading’s primary buyer, purchasing gold in Congolese francs. The arrangement is intended to support confidence in the local currency while increasing the country’s official gold reserves.
The approach also gives the state a more direct role in the domestic gold market, linking formalisation of artisanal production with reserve accumulation and monetary policy objectives.
For the government, the combination of local purchasing, traceable supply chains and domestic refining could strengthen oversight of gold flows and reduce dependence on informal export channels.
However, the effectiveness of the programme will depend on the ability to secure sufficient legally sourced supply, enforce traceability standards and attract buyers willing to transact through formal channels. The proposed LBMA certification for the Kinshasa refinery would also require the facility to meet the association’s applicable standards.
The planned facilities represent a further effort by the DRC to move beyond mineral extraction towards greater domestic processing and control over its gold value chain. Their eventual contribution will depend on construction, operational execution and the extent to which artisanal production can be brought into the formal market.