JOHANNESBURG, Nov 23 – A consortium led by Vitol’s Engen unit is planning a 40 billion rand ($2.3 billion) integrated liquefied natural gas (LNG)-to-power project in Durban, South Africa, with construction expected to begin in late 2028, as the country considers imported gas as part of its strategy to diversify electricity generation and address declining domestic supply.
The proposed development will combine an LNG import terminal, associated pipeline infrastructure and a 1.9-gigawatt (GW) combined-cycle gas turbine power plant. Vitol said the project remains conditional on the consortium’s successful participation in South Africa’s second gas-to-power procurement round, as well as the receipt of relevant regulatory and environmental approvals.
The consortium is led by Engen and includes VTTI, Vitol and Saudi Arabia’s ACWA Power. Its proposed location at Durban, on South Africa’s east coast, would establish an additional entry point for imported natural gas and connect LNG supply infrastructure with large-scale electricity generation.
LNG infrastructure and power generation
At the centre of the development is an LNG import terminal with a peak regasification capacity of approximately 5 billion cubic metres per annum. The facility would receive LNG shipments, convert the gas back into its gaseous state and supply it through associated pipeline infrastructure to the proposed power plant and potentially other consumers, subject to the final project configuration.
The 1.9GW combined-cycle gas turbine facility would use natural gas to generate electricity, with the combined-cycle process designed to improve efficiency by using waste heat from the initial gas-turbine stage to produce additional power.
The scale of the proposed generation capacity makes the project a significant planned addition to South Africa’s gas infrastructure. However, the development remains at the procurement and approvals stage, and its construction timetable will depend on the outcome of the relevant processes.
Vitol said the consortium expects construction to begin in late 2028, conditional on securing a place in the second gas-to-power procurement round. South Africa’s first round closed without any preferred bidders being announced, adding uncertainty to the timing and implementation of the next procurement process.
Declining Mozambican supply drives search for alternatives
South Africa currently sources most of its domestic natural gas from Mozambique. The rapid decline in feedstock from that supply route is increasing pressure on the country to identify alternative sources as existing gas availability tightens.
Imported LNG is emerging as one option. An import terminal at Durban could allow South Africa to access international gas markets and diversify supply beyond its existing pipeline-dependent arrangements.
The proposed project is therefore linked to a broader energy transition challenge. South Africa continues to rely heavily on coal-fired power plants for electricity generation, but is exploring alternatives that can support electricity supply while its energy system evolves.
Gas-fired generation can provide dispatchable electricity, meaning output can be adjusted to meet changes in demand and complement variable renewable sources such as wind and solar. However, the extent to which imported LNG can contribute competitively will depend on international gas prices, shipping costs, terminal charges, pipeline access and the commercial terms secured for fuel supply.
Procurement and investment conditions
The consortium’s proposed construction timetable remains subject to South Africa’s second gas-to-power procurement round. The absence of preferred bidders from the first round highlights the importance of procurement design, project economics and the availability of bankable power-purchase arrangements.
For a project of this scale, the ability to secure long-term gas supply and predictable revenue from electricity sales will be central to financing and implementation. Regulatory approvals, environmental assessments and the development of supporting pipeline infrastructure will also determine whether the project advances as planned.
The participation of Vitol, VTTI and ACWA Power brings together companies with experience across energy trading, infrastructure and power development. Their involvement provides a potential platform for integrating LNG procurement, import infrastructure and electricity generation within a single development.
South Africa’s evolving gas strategy
The Durban proposal reflects South Africa’s effort to establish imported LNG as part of a more diversified energy mix. The country faces the challenge of managing declining gas availability while maintaining reliable electricity supply and reducing its dependence on coal-fired generation over time.
The project could provide additional gas import capacity and new electricity generation infrastructure if it secures the necessary procurement award, approvals and financing. It could also create a platform for broader gas-market development around Durban, depending on future demand and access to the terminal and pipeline network.
Nevertheless, imported LNG introduces exposure to international commodity price volatility and foreign exchange costs. Its long-term contribution to South Africa’s electricity system will depend on whether gas-fired power can remain commercially viable alongside coal, renewables and other emerging energy technologies.
The proposed 40 billion rand development therefore represents a potential expansion of South Africa’s energy infrastructure, but its progression from proposal to construction will depend on procurement outcomes, regulatory clearance and the ability of the consortium to establish a sustainable commercial framework.