NAIROBI, Nov 18 – Sahara Group, through its subsidiary Asharami Synergy Kenya Limited, is developing a 30,000-metric-tonne liquefied petroleum gas (LPG) import, storage and handling terminal in Changamwe, Mombasa, as Kenya seeks to expand access to cleaner cooking fuels and strengthen its domestic energy supply chain.
The facility, scheduled for completion in 2028, is expected to support access to affordable cooking gas for 10 million homes by that year. It will also strengthen Mombasa’s role as a regional distribution hub serving East and Central African markets.
According to a statement by Sahara Group, the terminal will occupy 23.19 acres at the Kenya Petroleum Refineries Limited (KPRL) site. The investment is aligned with Kenya’s LPG Growth Strategy and broader clean-cooking objectives.
Storage capacity targets lower supply costs
Speaking at the groundbreaking ceremony, Bayo Sotomi, Country Manager of Asharami Synergy Kenya, said the additional storage capacity would enable larger LPG cargoes, improve vessel discharge efficiency and reduce shipment and demurrage costs.
He said the project would strengthen access to cleaner energy while reducing reliance on traditional cooking fuels.
“The 30,000-metric-tonne LPG storage facility is a major economic boost that will accelerate the energy supply chain. It will ensure lower prices for distribution of clean energy in schools and hospitals and restore forests from firewood cutting.”
Sotomi added that Asharami would collaborate with government agencies, regulatory authorities and local technical institutions to provide internships, industrial attachments and training in LPG handling, engineering and safety.
The terminal is also expected to support regional distribution, with potential supply markets including Uganda, Rwanda, Burundi, South Sudan and eastern Democratic Republic of Congo.
Kenya targets wider household access to LPG
Also speaking at the ceremony, Harsama Kello, Principal Secretary for the State Department for Petroleum, said the investment would contribute to transforming Kenya’s energy supply chain.
Kello said 70% of Kenyans still relied on kerosene, charcoal and firewood for cooking. He noted that the government was pursuing its National LPG Growth Strategy Programme to expand access to cleaner energy.
He said the project would create employment opportunities for residents of Changamwe and help reduce the cost of cooking gas for households.
“By 2028, we want to make that a reality in homes. Launching Asharami LPG is one of the plans to make Kenya self-sufficient in gas supply,” he said.
KPRL and energy regulator highlight project benefits
Tom Mailu, General Manager of Kenya Petroleum Refineries Limited, said the project would comply with environmental requirements and assured that local residents would benefit from the investment. He said the development was expected to take 24 months.
Lillian Mahiri Zaja, KPRL Board Chair, said the facility would also help protect the company’s assets.
“The future of the energy sector will be shaped by institutions we build for the country and for the future of our people,” she said.
Eng. Edward Kinyua, Director-General of the Energy and Petroleum Regulatory Authority (EPRA), described the multi-billion-shilling facility as an investment that would support economic growth.
He also identified indoor air pollution as a major public health concern, citing an estimated 25,000 deaths, and said the project supported government efforts to move households away from biomass fuels towards LPG.
With its planned 2028 completion, the terminal is expected to add substantial import and storage capacity to Kenya’s LPG infrastructure while supporting the country’s clean-cooking programme and Mombasa’s regional distribution role.